"4.29" railway traffic accidents (1997)

Seven , accident learned and recommendations
Lessons from this accident is painful . Accident numbers reflect rongjiawan times work area field operations out of control, signal interlocking lack of effective means of monitoring device when the device is subjected to vandalism , it can not be effectively monitored , but also exposed lax management Changsha electricity department , prevent ineffective .
To draw lessons from the accident , it is recommended to take the following measures:
( A ) from the ideological understanding firmly establish the concept of safety first
Rail transport is very busy in the current circumstances, but also to correctly handle the relationship between safety and efficiency , and effectively solve the production and maintenance of equipment transport contradiction strengthen safety management, to ensure safety of railway transportation .
( Two ) from the technical means to take precautions
To increase scientific and technological content , advanced redundancy, improve signal interlock device reliability. Interlock device for computer monitoring to implement and realize automatic recording, automatic alarm, to maximize the level of monitoring equipment to prevent accidents caused by human factors .
( Three ) from strengthening management control to strengthen field operations
Affecting letter , together , increase the normal use of equipment maintenance operations should strictly implement the double operating system, strengthen mutual control post jobs , cars, inter-departmental joint control. Strict maintenance work contacts points registration system, strengthen routine maintenance and construction work inspection and guidance on safety management plug slipping through the net , earnestly implement various security measures
( Four ) to reform the current system of signal maintenance
In order to solve the contradiction equipment maintenance and utilization , to reform the existing signal maintenance system, to change the current use of headway , sporadic point method of repair , signaling equipment necessary repair work included monthly transport plan or an open " sunroof " repair method .
( Five ) to strengthen the security key parts of the guard
In this accident as lesson immediately within the scope of the whole road to carry out an extensive "anti- illegal , anti-sabotage , safety, ensuring smooth traffic " campaign to strengthen the railway public security and safety key parts of the prevention, strict key types of personnel review and control, improve the political acumen of the workers and vigilance to prevent damage, particularly to guard against damage during production operations .
| Updated:2013.10.16    Source:    Clicks:2310